Built for the way your line actually runs.
A complete turnkey water pouch plant: RO water treatment, multiple form-fill-seal pouch machines, QC laboratory, BIS and FSSAI documentation, civil layout and operator training.
Buying a pouch machine is not the same as starting a pouch water business. The machine is roughly a third of what a licensed operation needs — the rest is the RO water house sized for your output, the hygienic room the machines must sit in, the QC laboratory BIS requires, the daily test records, and the certification process itself. This turnkey scope covers all of it, including the civil layout drawing and the operator training that determines whether your seal rejection rate sits at 1% or 8%. Typical configurations run two to six pouch machines off a single water house.



Who this configuration suits.
Get a detailed quote for the Turnkey Pouch Plant.
Layout drawing, utility schedule, BIS / FSSAI checklist, itemised quotation in 24 hours.
Everything we ship with this plant.
Standard turnkey scope. Optional add-ons quoted on request.
Specs at a glance.
| Output | 80 – 480 pouches/minute (2–6 machines) |
| Daily output | 40,000 – 230,000 pouches (single shift) |
| Pouch size | 200ml standard, 100ml–500ml options |
| RO capacity | 1000 – 5000 LPH |
| Power load | 25 – 70 kW |
| Footprint | 2,000 – 4,000 sq.ft. |
| Manpower | 6 – 14 per shift |
| Commissioning | 4 – 7 weeks from PO |
| Compliance | BIS IS 14543 + FSSAI, documentation included |
Price on Request.
Every plant is quoted against your capacity, feedwater analysis, plot and product mix. Send us those and you get an itemised proposal within 24 hours.
Output, degree of automation and whether you need redundancy on critical stations.
A high-TDS, iron-heavy or seasonal input changes the treatment train and its cost materially.
Machinery only, or turnkey with civil drawings, utilities, commissioning and BIS / FSSAI documentation.
Number of SKUs, bottle sizes and how fast you need to switch between them.
Common questions.
How quickly can a pouch plant start production?+
Machinery commissioning is 4–7 weeks from PO. BIS certification runs in parallel and is usually the longer path — plan on production for stock before certification completes, and first legal sale after.
How many machines should I start with?+
Two, in almost every case. One machine leaves you with zero redundancy — a jaw failure stops the business. Two machines let you run one and service the other, and the incremental cost over one machine is small relative to the water house.
